Construction Update - June 2026
It’s the third year of Meyokumin Neighbourhood and Alley Renewal construction is underway. Work will consist of reconstruction and paving of the roads, removal and replacement of public sidewalk, curb, gutter and street lighting.
Front Street Construction
Work is ongoing in the following locations:
- Catchbasin replacements and relocations on 19 Avenue from 50 Street to 54 Street, and on 54 Street from 19 Avenue to Mill Woods Road S
- Pouring concrete sidewalk and driveway on the north side of 22 Avenue from 57 Street to 52 Street, the east side of 52 Street from 22 Avenue to 19 Avenue, the west side of 19A Avenue from 56 Street to 55 Street, the west side of 54 Street from 19 Avenue to 18 Avenue and the south side of 19 Avenue from 54 Street to 50 Street
- Paving on 62 Street from Mill Woods Road S to the south intersection of 18 Avenue
- Pouring concrete infrastructure for the Corner Store complex at the intersection of 19A Avenue and 57 Street
Upcoming work is occurring in the following locations:
- Sidewalk removal on the south side of 22 Avenue from 57 Street to 52 Street, the west side of 52 Street from 22 Avenue to 19 Avenue, the east side of 19A Avenue from 56 Street to 55 Street, the east side of 54 Street from 19 Avenue to 18 Avenue and the north side of 19 Avenue from 54 Street to 50 Street
- Road removal on 62 Street from 18 Avenue to the Corner Store complex entrance at 19A Avenue and 57 Street
- Milling and paving the parking lot at the Corner Store complex, located at the intersection of 19A Avenue and 57 Street
Open Spaces Construction
As part of Neighbourhood Renewal, the City is upgrading Meyokumin Park. The northwest side of the park is expected to be fenced off and closed to the public starting mid-June.
Progression of Work
The contractor working for the City has developed a map to show the progression of work, including scheduled closures.
Check out the links below to prepare for construction:
The City of Edmonton and EPCOR are working together to construct Low Impact Development, which will help with stormwater retention and help mitigate flooding.
If you live in the 2026 construction area, please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. All residents and business owners are asked to access their homes and businesses through the back entrances and alleys, where possible, during construction. If no alley access is available and/or you have special access requirements (such as DATS or a temporary access ramp to the front of your home), please contact the Construction Project Manager, David Ha, 780-496-4055, to coordinate.
Construction in Meyokumin began in spring 2024 and is expected to take 3 years (planned completion late fall 2026). Neighbourhood renewal in Meyokumin is progressing on time and on budget.