Construction Update - July 2026
Due to recent record rainfall events, the remaining landscaping work has been delayed due to wet conditions. Crews will continue to complete areas as conditions allow.
Main page content begins here
Neighbourhood and Alley Renewal construction is underway in Gariepy.
Due to recent record rainfall events, the remaining landscaping work has been delayed due to wet conditions. Crews will continue to complete areas as conditions allow.
Due to an unfortunate technical issue, information for people who were previously signed up for project updates was deleted.
If you’d like to receive email updates throughout Gariepy Neighbourhood Renewal construction, please sign up again, even if you were signed up previously.
We commit to using your feedback to inform communication during construction.
As part of the Gariepy Neighbourhood Renewal, the community has the option to receive decorative street blades throughout the neighbourhood at no additional cost to property owners.
Gariepy residents voted at the Preparing for Construction event and online and selected Option 2.
Neighbourhood Renewal rehabilitates residential roads, replaces street lights, sidewalks, curbs and gutters, and adds missing sidewalk links, where possible. Other opportunities to improve how people walk, bike, roll, drive and gather in the neighbourhood, and how they enjoy City-owned parks and open spaces are also explored.
Alley Renewal is part of the Gariepy neighbourhood reconstruction. Alley Renewal involves alley reconstruction and repaving, improvements to surface drainage where possible and upgrading of existing alley lighting to LED fixtures. Utility assessments and repairs, along with removals and pruning of trees and shrubs, are also completed.
A series of public events were carried out by the Project Team which gave community members the opportunity to build a project Vision and Guiding Principles together and provide regular feedback on the different stages of the project, including design.
Arterial roads are not included in the scope of work.
Neighbourhood Renewal construction in Gariepy has wrapped up for the 2025 construction season!
Construction began in May 2025 and was finished the fourth week of October. The 2025 construction season was a success, and we completed the majority of the planned construction, including the reconstruction of roads, sidewalks, curbs and gutters in the following areas:
There was some work in the 2025 construction area that was not completed. The installation of new streetlights is being coordinated with EPCOR and is scheduled for completion by spring of 2026. Work remains ongoing at the two pedestrian bridges over Gariepy Ravine. The bridges are currently being installed and will be open for public use in late November 2025. Due to seasonal constraints, the remaining path and landscaping work around the bridges is scheduled to be completed in the spring of 2026.
Construction of new sidewalks is on schedule. Road reconstruction has begun on 57 Avenue and 172 Street, which will result in localized road closures. The replacement of street lights and poles is now tentatively scheduled for November, dependent on EPCOR crew availability.
Work on the new sidewalks is progressing on schedule. Work has begun on the reconstruction of 57 Avenue and 172 Street roadways and will have localized road closures. The replacement of the street lights and poles is scheduled to start in September, depending on coordination with EPCOR.
A full road closure of 57 Avenue from 175 Street to Lessard Drive is now in place. This closure will be in effect until August 29, 2025. Refer to the sketch for the affected areas and follow posted detours.
All of the drainage replacements and relocations have been completed. Work on the new sidewalks are progressing on schedule. The paving of Gariepy Crescent is underway and will be completed shortly. The road reconstruction of 57 Avenue in front of Centennial School is currently underway and is proceeding on schedule. The replacement of the street lights and poles is scheduled to start at the end of August, depending on coordination with EPCOR.
The work in Gariepy Park and Top of Bank Park (along 53 Avenue and Lessard Drive) has also started. This work is being delivered by a separate contractor and will be monitored by Open Space Infrastructure Delivery.
The majority of the drainage replacements and relocations have been completed. Work on the new sidewalks is progressing on schedule. The replacement of the roadways is scheduled to start on select streets starting the end of July. The replacement of the street lights and pole is scheduled to start at the end of July.
The majority of the drainage replacements and relocations have been completed. Work on the new sidewalks is progressing on schedule. The replacement of the roadways is scheduled to start on select streets starting the end of June.
Work in Gariepy Park and Top of Bank Park (along 53 Avenue and Lessard Drive) has also started. This work is being delivered by a separate contractor and will be monitored by Open Space Infrastructure Delivery.
A Local Improvement is a construction project undertaken near or adjacent to residents’ properties which is considered more beneficial to the property owner and local area than to the City as a whole. These include upgrades to street lights and sidewalks.
Residents in Gariepy chose not to pursue decorative street lights, but had the opportunity to participate in the sidewalk Local Improvement decision.
Property owners were mailed a local improvement package dated January 31, 2024 which included information about the sidewalk reconstruction Local Improvement and a form for those who wished to petition against. The 30-day petition period has since expired. Since the City did not receive majority (50% +1) petitions against the Local Improvement, sidewalk reconstruction will take place in all project areas over 2 years of construction for the neighbourhood.
Neighbourhood Renewal construction in the Gariepy neighbourhood has wrapped up for the 2024 construction season!
Construction began in May of 2024 and was finished the third week of October. The 2024 construction season was a success and we completed most of the planned construction including the reconstruction of roads, sidewalks, curbs and gutters in the following areas:
There are some areas in the 2024 construction area that were not completed. Those include the installation of new street lights and the construction of the new path in the Top of Bank Park. The outstanding work will be completed when construction resumes in 2025.
The landscaping following the road and sidewalk reconstruction is being delivered by a separate contractor and will be monitored by the Project Team. Landscaping work is highly dependent on weather and sod availability. Sod is expected to be completed this year, with the exception of the Top of Bank Park, which will be completed once the shared path is constructed in 2025.
Neighbourhood Renewal work will resume in Gariepy in the first week of May 2025, weather permitting. The planned scope for 2025 will include the reconstruction of roads, sidewalks, curbs and gutters in the following areas:
Prior to work resuming, construction notifications will be delivered to impacted residences.
Thank you for your patience and understanding as we completed another successful year of Neighbourhood Renewal construction. Construction in Gariepy began in 2024 and is expected to take 2 years.
Gariepy Neighbourhood Renewal consists of reconstruction and paving of the roads and removal and replacement of public sidewalks, curbs, gutters and street lighting.
Construction began in May 2024 in the 2024 area and is progressing on schedule. The sidewalk construction is mainly complete, with some driveway connections still remaining.
The base lift of asphalt has been completed on all sections of the roads. The final lift of asphalt will be completed the first week of October, depending on weather. The construction of the remaining 3 continuous crossings will be coordinated with the remaining asphalt paving. All construction activities are on schedule to be completed by the middle of October.
The landscaping behind the renewal work is being handled by a separate contractor. Work is scheduled to start shortly, with topsoil being placed in all excavated areas.
Sod will be placed depending on weather and timelines. Not all areas may receive sod before the end of the season. Areas that don’t receive sod in 2024 will be completed when 2025 construction begins.
Check out the links below to prepare for construction:
Please watch your mailbox for construction bulletins that will provide more information along with details on landscaping and access. For special concerns or access requirements, such as DATS, please contact the Construction Project Manager, Mr. Courtney Beamish, at 780-496-4055.
Planning and design has been underway for Gariepy Neighbourhood and Alley Renewal since January 2022. The Project Team has worked to create a design that meets current City standards, policies and technical considerations and considers public input.
We presented the final design to the community in September 2023 and now the time has come to start preparing for construction!
We invite you to learn and ask questions about construction and share your feedback and perspectives to identify potential impacts you may experience during construction
Planning and design has been underway for Gariepy Neighbourhood and Alley Renewal since January 2022. The Project Team has worked to create a design that meets current City standards, policies and technical considerations and considers public input.
We presented the final design to the community in September 2023 and now the time has come to start preparing for construction!
We invite you to learn and ask questions about construction and share your feedback and perspectives to identify potential impacts you may experience during construction.
Year Split Map
Thank you to everyone who engaged with the Project Team during the Community Feedback on Final Design stage of Gariepy Neighbourhood and Alley Renewal. The online survey closed on October 8, but you can still review the
The public engagement activities and participation are summarized in the
The report for the Community Feedback on Draft Design stage is also ready. We are committed to using the feedback from the previous stage to shape the final design for Gariepy.
Your feedback will be considered as we finalize the design for Gariepy Neighbourhood and Alley Renewal. We will be reaching out to you again in spring 2024 as we enter the Preparing for Construction stage of Neighbourhood Renewal.
Thank you to everyone who engaged with us during the Community Feedback on Draft Design stage of Gariepy Neighbourhood and Alley Renewal! The survey is now closed, but you can still review draft design images and videos below.
A What We Heard Report will be released in the coming months summarizing your feedback on the draft design, but the engagement summary is available now.
Review design package
In fall 2022, we were in the Exploring Options and Tradeoffs stage of Neighbourhood and Alley Renewal where we shared design features and explained the tradeoffs of those options. The (12MB) for that stage is now available.
The Gariepy Project Team has been working to come up with a set of options for renewing Gariepy’s roads, sidewalks, alleys, street lights and open spaces, using the input you provided us in the spring. We are now weighing these options with the associated tradeoffs.
To do this, we need your input!
Review the Options and Tradeoffs proposed for Gariepy
Review the Exploring Options and Tradeoffs Engagement Summary
Thank you to everyone who engaged with us on the Building a Project Vision Together and Exploring Opportunities stages of the project. We appreciate everyone who took the time to provide feedback through the online survey and community conversations and participated in the virtual workshop and community walk.
The community survey and events have concluded. Thank you to everyone who engaged with the online survey from March 8 - 27, 2022 and participated in the virtual workshop and community walk.
Neighbourhood and Alley Renewal is coming to Gariepy and planning is underway!
Learn about Gariepy Neighbourhood and Alley Renewal and what’s coming. More details about the first community-wide engagement opportunity will be sent out in March 2022.
Landscaping construction as part of Gariepy Neighbourhood Renewal is scheduled to begin May 5, weather permitting.
Landscaping work from 2025, which was incomplete due to seasonal limitations, is scheduled to be finished in spring 2026.
The two new pedestrian bridge structures over Gariepy Ravine are complete. Asphalt trail connections and landscaping around the bridges will be completed in spring 2026.
Landscaping for boulevards and along new asphalt trails will be completed as soon as possible, weather permitting. Incomplete residential front yard landscaping will be completed in early 2026 once sod is available. All work is expected to be completed in early 2026.
| Title | Delivery Project Manager |
|---|---|
| courtney.beamish@edmonton.ca |
All additional inquiries or escalations can be directed to the Building Great Neighbourhoods team by calling 780-496-4055 or through 311.