Pleasantview neighbourhood renewal construction is mainly complete.

Construction update - August 2024

Pleasantview Neighbourhood Renewal includes reconstruction and paving of the roads, removal and replacement of public sidewalks, curbs, gutters and street lighting.

So far in 2024, construction in the following areas is complete:

  • 60 Avenue west of 110 Street road work
  • 60 Avenue from 110 Street to 109 street traffic circle road work
  • 60 A Avenue from 61 Avenue to 106 Street road work
  • Raised crosswalks along 109 Street
  • Installation of the official off-leash dog park fence, gates and site furniture 

Concrete, road and landscaping work is set to be complete before the end of the year on 60 Avenue from 110 Street to 111 Street, as well as concrete median and asphalt work on 109 Street from 60 Avenue to 61 Avenue.

Thank you for your patience and understanding as we complete the remaining scope of work. Construction in Pleasantview neighbourhood began in summer of 2022 and is now complete, except for the locations identified above. 

About the Project

The Neighbourhood Renewal program will rehabilitate roads, replace street lights, curbs and gutters, repair sidewalks, and connect missing sidewalk links where possible. Other opportunities to improve parks and public spaces will also be explored.

Cost sharing opportunities will be made available through the Local Improvement process for sidewalk reconstruction and decorative street light upgrades in the neighbourhood. Arterial roads and alleys are not included in the scope of work.

A series of public events will be scheduled by the project team which will give residents the opportunity to build a project vision and guiding principles together and provide regular feedback on the different stages of the project including design.

Please watch your mailbox for correspondence from Building Great Neighbourhoods and Open Spaces about the Pleasantview Neighbourhood Renewal Project.

Neighbourhood Reconstruction