Valley Line West is a 14-km LRT extension from downtown to Lewis Farms. Marigold Infrastructure Partners is in its fourth year of major construction. Construction is anticipated to be complete in 2028, followed by testing before the line can open.

Accelerated roadwork to begin in mid/late April 

Accelerated roadwork and track work in key areas will occur throughout 2025, and will reduce the overall duration of traffic restrictions by more than half. This plan will allow Marigold to complete the majority of roadwork in 2025, and get many of the roads into their final configuration. 

A three-phased approach from mid/late April to November, 2025 will impact several major intersections and corridors, including:

Phase 1

When Phase 1 is complete at each of the intersections, traffic lanes will begin to open. However, Marigold will continue to work in the area, and minor traffic restrictions will remain in place until the end of the construction season, allowing Marigold to complete as much work as possible. In addition to the accelerated roadwork, Marigold will also continue to work at many other locations and facilities along the alignment. 

Phase 2 (July-September, 2025)

  • 104 Avenue (105 to 121 Street) - reduced to one lane eastbound and westbound
  • Stony Plain Road at 142 Street (partial closure)
  • 95 Avenue at 156 Street (partial closure)

Phase 3 (September-November, 2025)

  • 104 Avenue (105 to 121 Street) - reduced to one lane eastbound and westbound
  • Stony Plain Road at 149 Street (partial closure)

Ongoing communication with stakeholders and businesses will continue in order to find collaborative solutions to maintain access to businesses. A public communications plan has been developed to proactively inform Edmontonians about the traffic restrictions and alternative routes. Details on Phases 2 and 3 will be released as soon as they are confirmed. Read the full Council report.